Lendrum Development
Civida’s newest re-development, Lendrum, is located at 11442 60 Ave. NW. Nestled in a welcoming, family-friendly community in southwest Edmonton and within walking distance of South Campus/Fort Edmonton Park Transit Centre, Lendrum is home to over 120 families and individuals.
Amenities include underground parking, in-suite laundry, common room, courtyard, nearby schools, LRT access and much more.
All homes at Lendrum were completed in October 2023.
Learn more about Lendrum.
For more information, contact [email protected] or 780-702-4545. You can also apply online.
Background
Civida re-developed two aging community housing apartment complexes in the Lendrum Place neighbourhood in south west Edmonton. These complexes, which had reached the end of their lifespan, were built in the early 1960’s and served the community of Lendrum for over 50 years. The complex more than doubled the original site’s density.
The new development was designed with extensive community input, in partnership with the City of Edmonton, to meet the needs of those waiting for affordable housing in our city. Construction began in 2021, and was completed in October 2023.
Lendrum tenants are proud to call this new development home.
About our suites
Homes at Lendrum have beautiful, modern and durable finishings and come with amenities such as in-suite laundry, underground parking, a multi-purpose room with a private patio and direct access to the LRT. For more information about our Lendrum suites, please see our Photos and Floor Plans section.
Features
Our Lendrum complex is located on 114 Street and 60 Avenue, and consists of two-storey walkout townhomes with apartments above. There are 120 homes at Lendrum, including 25 one-bedroom units, 48 two-bedroom units, 31 three-bedroom units and 16 four-bedroom units including 11 two-storey walkout townhomes.
Design elements
- Underground parkade
- Bicycle storage
- In-suite laundry
- Site office
- 12 barrier-free suites
- Multi-purpose room with private patio
- Large, open courtyard
- Public pedestrian access path to LRT
- Metal cladding and brick veneer exterior
Floor plans
Click on an image to enlarge it.
Suite plans
Click on an image to enlarge it.
One-bedroom apartments
Two-bedroom apartments
Three-bedroom apartments
Four-bedroom apartments and townhouses
Project Timeline
- Public Consultation: October 2016 to March 2017
- Demolition of former buildings: December 2019
- Construction: October 2021 – October 2023
- Completion and Occupancy: October – November 2023
Sod Turning, 2020
Project construction began, Fall 2021
January 2022
Photos and videos supplied by Graham Construction.
October 2022
Photos supplied by Graham Construction.
November 2022
Photos supplied by Graham Construction.
October 2023
Project completion and occupancy.
Thank you for joining the conversation.
We were committed to a planning and redevelopment process that is inclusive, transparent and driven by our values. Over the course of this project we engaged residents, families, neighbours, businesses, organizations, community partners and the public in a meaningful way that generated a shared sense of commitment to this site redevelopment. Through collaboration and engagement we had the opportunity to have a positive impact in the community that this housing complex is a part of.
Guiding Principles
Throughout the engagement we:
- Ensured the timely sharing of project information that provided all stakeholders and interested parties with complete, objective and reliable information,
- Engaged and gathered feedback, opinions and perspectives at various stages in the development of the site, and;
- Clearly demonstrated our commitment to engaging the public and incorporating their input into the project.
Public Consultations
Using a phased approach, between October 2016 and April 2017 we hosted open houses and public meetings in the Lendrum community to enable people to contribute to and be engaged in this project. Through these consultations we shared information and provided people with the opportunity to learn, ask questions, share thoughts, discuss ideas and review concepts.
Where We Are Now
Post Consultation
Our public consultations ended, as the project is complete. Civida continues to work with the City of Edmonton to ensure there is conformance to city guidelines and regulations. Read the final What We Heard Summary Report here >>